PERSONA 3 BEDROOM (NORTH TOWER) PHASE – I | |||
STRUCTURE WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Foundation | 100% | – |
2- | 2 Parking Slab | 100% | – |
3- | Parking Plaster | 98% | 2% |
4- | Parking Flooring | 50% | 50% |
5- | 17 Typical Slab Structure | 100% | – |
FINISHING WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Block Masonary | 100% | – |
2- | Plaster Internal | 100% | – |
3- | Plaster External | 100% | – |
4- | Plumbing Work | 95% | 5% |
5- | Electrical Work | 95% | 5% |
6- | Bathroom Tiling Work | 95% | 5% |
7- | Floor Tiling Work | 95% | 5% |
8- | Color Internal | 50% | 50% |
9- | Color External | 95% | 5% |
INNOVA 4 BEDROOM (SOUTH TOWER) PHASE – I | |||
STRUCTURE WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Foundation | 100% | – |
2- | 2 Parking Slab | 100% | – |
3- | Parking Plaster | 98% | 2% |
4- | Parking Flooring | 50% | 50% |
5- | 20 Typical Slab Structure | 100% | – |
FINISHING WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Block Masonary | 100% | – |
2- | Plaster Internal | 100% | – |
3- | Plaster External | 100% | – |
4- | Plumbing Work | 95% | 5% |
5- | Electrical Work | 95% | 5% |
6- | Bathroom Tiling Work | 95% | 5% |
7- | Floor Tiling Work | 95% | 5% |
8- | Color Internal | 50% | 50% |
9- | Color External | 95% | 5% |
PERSONA 3 BEDROOM (EAST TOWER) PHASE – II | |||
STRUCTURE WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Foundation | 100% | – |
2- | 2 Parking Slab | 100% | – |
3- | Parking Plaster | 98% | 2% |
4- | Parking Flooring | 50% | 50% |
5- | 20 Typical Slab Structure | 65% | 35% |
FINISHING WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Block Masonary | 65% | 35% |
2- | Plaster Internal | 50% | 50% |
3- | Plaster External | 50% | 50% |
4- | Plumbing Work | – | 100% |
5- | Electrical Work | – | 100% |
6- | Bathroom Tiling Work | – | 100% |
7- | Floor Tiling Work | – | 100% |
8- | Color Internal | – | 100% |
9- | Color External | 15% | 85% |
INNOVA 4 BEDROOM (WEST TOWER) PHASE – II | |||
STRUCTURE WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Foundation | 100% | – |
2- | 2 Parking Slab | 100% | – |
3- | Parking Plaster | 98% | 2% |
4- | Parking Flooring | 50% | 50% |
5- | 17 Typical Slab Structure | 70% | 30% |
FINISHING WORK | |||
Description | Completed Work | In Progress Work | |
% | % | ||
1- | Block Masonary | 30% | |
2- | Plaster Internal | 60% | 40% |
3- | Plaster External | 50% | 50% |
4- | Plumbing Work | – | 100% |
5- | Electrical Work | – | 100% |
6- | Bathroom Tiling Work | – | 100% |
7- | Floor Tiling Work | – | 100% |
8- | Color Internal | – | 100% |
9- | Color External | 15% | 85% |
NOTE :- | |||
Ø Bathrooms fiting , Fixture, Internal Doors , Electrical Switches will be fixed just before possession. | |||
Ø Landscaping work, Reception Building & Club House Building are in Progress. |