Work Status

PERSONA 3 BEDROOM (NORTH TOWER) PHASE – I
       
  STRUCTURE WORK    
       
  Description Completed Work In Progress Work
    % %
1- Foundation 100%
2- 2 Parking Slab 100%
3- Parking Plaster 98% 2%
4- Parking Flooring 50% 50%
5- 17 Typical Slab Structure 100%
       
  FINISHING WORK    
       
  Description Completed Work In Progress Work
    % %
1- Block Masonary 100%
2- Plaster Internal 100%
3- Plaster External 100%
4- Plumbing Work 95% 5%
5- Electrical Work 95% 5%
6- Bathroom Tiling Work 95% 5%
7- Floor Tiling Work 95% 5%
8- Color Internal 50% 50%
9- Color External 95% 5%
INNOVA 4 BEDROOM (SOUTH TOWER) PHASE – I
  STRUCTURE WORK    
       
  Description Completed Work In Progress Work
    % %
1- Foundation 100%
2- 2 Parking Slab 100%
3- Parking Plaster 98% 2%
4- Parking Flooring 50% 50%
5- 20 Typical Slab Structure 100%
       
  FINISHING WORK    
  Description Completed Work In Progress Work
    % %
1- Block Masonary 100%
2- Plaster Internal 100%
3- Plaster External 100%
4- Plumbing Work 95% 5%
5- Electrical Work 95% 5%
6- Bathroom Tiling Work 95% 5%
7- Floor Tiling Work 95% 5%
8- Color Internal 50% 50%
9- Color External 95% 5%
PERSONA 3 BEDROOM (EAST TOWER) PHASE – II
  STRUCTURE WORK    
       
  Description Completed Work In Progress Work
    % %
1- Foundation 100%
2- 2 Parking Slab 100%
3- Parking Plaster 98% 2%
4- Parking Flooring 50% 50%
5- 20 Typical Slab Structure 65% 35%
       
  FINISHING WORK    
  Description Completed Work In Progress Work
    % %
1- Block Masonary 65% 35%
2- Plaster Internal 50% 50%
3- Plaster External 50% 50%
4- Plumbing Work 100%
5- Electrical Work 100%
6- Bathroom Tiling Work 100%
7- Floor Tiling Work 100%
8- Color Internal 100%
9- Color External 15% 85%
INNOVA 4 BEDROOM (WEST TOWER) PHASE – II
  STRUCTURE WORK    
       
  Description Completed Work In Progress Work
    % %
1- Foundation 100%
2- 2 Parking Slab 100%
3- Parking Plaster 98% 2%
4- Parking Flooring 50% 50%
5- 17 Typical Slab   Structure 70% 30%
       
  FINISHING WORK    
       
  Description Completed Work In Progress Work
    % %
1- Block Masonary   30%
2- Plaster Internal 60% 40%
3- Plaster External 50% 50%
4- Plumbing Work 100%
5- Electrical Work 100%
6- Bathroom Tiling Work 100%
7- Floor Tiling Work 100%
8- Color Internal 100%
9- Color External 15% 85%
       
  NOTE :-    
       
  Ø Bathrooms fiting , Fixture, Internal Doors , Electrical Switches will be fixed just before possession.
  Ø Landscaping work, Reception Building & Club House Building are in Progress.